Timeline

  1. Late 2021

    $4 million committed to jump-start project. Enables development of 30% engineering designs and drafting of required environmental documentation (Environmental Impact Report, or EIR).

  2. March 2022

    Consultant team hired, project kickoff

  3. July 2022 – September 2023

    Data collection and alternative development including:

  4. October 2023

    Conceptual Alternatives Feasibility Analysis completed to analyze first set of project alternatives.

  5. October 10, 2023

    California Environmental Quality Act (CEQA) process initiated by releasing a Notice of Preparation (NOP) for an EIR. The NOP provided an overview of the scope and nature of the project and invited comments from stakeholders through November 30, 2023.

  6. November 2, 2023
  7. November 2023 – April 2024

    NOP comments reviewed, feedback synthesized, internal evaluation of further studies needed, and exploration of additional project alternatives.

  8. May 9, 2024

    U.S. Army Corps of Engineers Interagency Meeting

  9. May 2024

    Engagement consultant hired. Executed new task order to complete the analyses required to identify the Least Environmentally Damaging Practicable Alternative (LEDPA) before beginning the EIR.

  10. July 2024

    Community Conversations held to inform Outreach and Engagement Plan. Updated draft project alternatives based on feedback and additional analysis.

  11. August 2024

    Draft Outreach and Engagement Plan presented to the OneShoreline Board.

  12. September – December 2024

    Engagement on updated draft project alternatives.

  13. January – March 2025

    Analyze community feedback on draft alternatives, refine alternatives, continue outreach

  14. Summer 2025

    Establish preferred alternative and begin EIR and CEQA analysis, continue outreach

  15. Fall 2025

    Regulatory agency engagement

    Concept Design

    Begin Draft Environmental Impact Report and LEDPA Analysis

  16. Late Spring / Early Summer 2026

    Release Draft Environmental Impact Report for Public Review and Comment

    Initiate project phasing and financing planning

  17. 2026 – 2028

    Complete Project Design