Timeline
-
Late 2021
$4 million committed to jump-start project. Enables development of 30% engineering designs and drafting of required environmental documentation (Environmental Impact Report, or EIR).
-
March 2022
Consultant team hired, project kickoff
-
July 2022 – September 2023
Data collection and alternative development including:
- LiDAR flyover to update the project area’s topography and bathymetry data;
- Reports summarizing the Project’s environmental constraints (e.g. biological resources and hazardous materials), coastal flood hazards, and inland flood hazards; completed a corrosion study.
- Series of project alternatives identified and meetings conducted with shoreline developers, subject matter experts, and environmental regulatory staff to facilitate early input.
-
October 2023
Conceptual Alternatives Feasibility Analysis completed to analyze first set of project alternatives.
-
October 10, 2023
California Environmental Quality Act (CEQA) process initiated by releasing a Notice of Preparation (NOP) for an EIR. The NOP provided an overview of the scope and nature of the project and invited comments from stakeholders through November 30, 2023.
-
November 2, 2023
Public meeting held. Materials from this meeting can be found below and on the OneShoreline event calendar.
-
November 2023 – April 2024
NOP comments reviewed, feedback synthesized, internal evaluation of further studies needed, and exploration of additional project alternatives.
-
May 9, 2024
U.S. Army Corps of Engineers Interagency Meeting
-
May 2024
Engagement consultant hired. Executed new task order to complete the analyses required to identify the Least Environmentally Damaging Practicable Alternative (LEDPA) before beginning the EIR.
-
July 2024
Community Conversations held to inform Outreach and Engagement Plan. Updated draft project alternatives based on feedback and additional analysis.
-
August 2024
Draft Outreach and Engagement Plan presented to the OneShoreline Board.
-
September – December 2024
Engagement on updated draft project alternatives.
-
January – March 2025
Analyze community feedback on draft alternatives, refine alternatives, continue outreach
-
Summer 2025
Establish preferred alternative and begin EIR and CEQA analysis, continue outreach
-
Fall 2025
Regulatory agency engagement
Concept Design
Begin Draft Environmental Impact Report and LEDPA Analysis
-
Late Spring / Early Summer 2026
Release Draft Environmental Impact Report for Public Review and Comment
Initiate project phasing and financing planning
-
2026 – 2028
Complete Project Design